Heating equipment installation
1 wood chip and pellet double boiler system 200 kW.
Approx. 170 m of double-pipe underground pipeline for local heating.
3 heat transfer stations approx. 50 kW.
3 fresh water stations, tap capacity 80/100 l/min.
Heating manifold and buffer tank.
Ca. 155 Ventilkompaktheizkörper.
Approx. 2,100 m pipe network heating, carbon steel, metal composite pipe. Insulation work on pipes and fittings.
Building management system in the central heating system.
Three new buildings with a total of approx. 142 rooms. 1 wood chip and pellet double boiler system 200 kW