The construction task is the refurbishment of a listed building in the city centre of Munich. The refurbishment is divided into several construction phases. The following specifications refer to electrical installation work in the areas of boxes, saunas and outdoor facilities.
execution dates;
Outdoor installations: 9.8.2021 — 17.9.2021;
Boxing and sauna: 30.8.2021 — 22.10.2021;
Core quantities;
Approx. 150 m cable tray;
Approximately 6 000 m cable;
Approximately 80 lighting fixtures
The construction task is the refurbishment of a listed building in the city centre of Munich. The refurbishment is divided into several construction phases. The following specifications refer to electrical installation work in the areas of boxes, saunas and outdoor facilities.
execution dates;
Outdoor installations: 9.8.2021 — 17.9.2021;
Boxing and sauna: 30.8.2021 — 22.10.2021;
Core quantities;
Approx. 150 m cable tray;
Approximately 6 000 m cable;
Approximately 80 lighting fixtures