Construction and installation of ventilation and air-conditioning systems for the construction of a new hospital building within an existing property
11 pcs supply air/exhaust air, combined central unit 1,500 - 13,000 m3/h;
1 pc supply air/exhaust air, central unit with KV system 7,100 m3/h;
4 St Einzelabluftventilatoren 150 - 900 m3/h;
2 St Außenluftansaugtürme 20.000 - 30.000 m3/h;
2 St Fortluftausblasturm 22.000 m3/h;
1 St Fortluftausblastürme 6.500 m3/h;
1 St Fortluftausblastürme 3.800 m3/h;
6,000 m2 air duct, galvanized;
3,300 m air duct, galvanized;
200 m air duct, plastic;
350 pcs Volumetric flow controller, galvanized;
380 pcs supply/exhaust ceiling air outlets;
350 pcs fire dampers with actuator;
5,500 kg steel structure;
1 pc smoke protection pressure system for safety stairwell, 30,000 m3/h;
1 pcs Mechanical smoke exhaust elevator shaft, 2,000 m3/h;
Operation of the entire system before and after VOB acceptance until handover to the operator for approx. 9 months.