New construction of the energy center with CHP, energy storage, social and sanitary facilities, as well as sludge dewatering and sludge water treatment (Deammonification).
Demolition in general:
- the buildings / structures are to be demolished including the foundation components,
- the demolition pits are finally to be filled with existing soil,
- Before the actual demolition work, the buildings are to clear out and to remove the building pollutants.
Total demolition sludge dewatering plant:
- year of construction: 1977,
- single storey, L x W x H approx. 45 x 14 x 7 m,
- Construction: Reinforced concrete skeleton made of prefabricated elements with lining,
- Saddle roof made of lightweight concrete slabs with trapezoidal sheet metal covering and KMF thermal insulation, façade with trapezoidal sheet cladding and KMF thermal insulation.
Known building pollutants:
- KMF insulation ("old mineral wool" in the sense of TRGS 521),
- wallcoverings with asbestos-cement fiber-cement panels,
- fire doors with asbestos products,
- asbestos-containing flange gaskets,
- Chlorinated joint sealants.
Total demolition low-pressure gas tank:
- year of construction: 1997,
- D x H approx. 13 x 11 m,
- Construction: Reinforced concrete floor slab, steel gas cylinder with chloroprene rubber (CR) membrane with polyamide fabric insert.
Total demolition gas compressor station:
- year of construction: 1998,
- single storey, L x W x H approx. 16 x 7 x 4 m,
- Construction: masonry, reinforced concrete floor slab, steel roof with trapezoidal sheet metal covering / cladding and KMF thermal insulation.
Known building pollutants:
- KMF insulation ("old mineral wool" in the sense of TRGS 521).