"Delivery and installation of the building automation systems for a laboratory building with 2 partial air conditioning systems, 6 full air conditioning systems (2 of them for S3 areas with high requirements for room pressure control, system availability and system response in the event of a fault), 20 special exhaust systems, approx. 200 fire dampers and approx. 500 volume flow controllers.
7,000 physical data points are to be processed via 30 automation stations according to DIN EN ISO 16484 (programming system controller according to IEC 61131-3). The systems must be connected to an existing management system (make INGA).
The services include all cable routing and field devices (approx. 140,000 m cable and 1,650 field devices). "