The subject of the contract is to develop a complete project documentation together with the acquisition of the necessary authorisation decisions for the implementation of road investment for the project:
“Construction of a communication system for the operation of the Wroclaw Sports Centre”.
As part of the order, you should develop:
1.1 The concept of road layout
1.2 Design documentation and obtain:
1.2.1. The decision to authorise the implementation of a road investment with the rigor of immediate feasibility with the division into stages together with a certificate of its finality.
1.2.2. Preparatory work
a) Acquisition of maps for design purposes
b) The concept of road layout taking into account the W3 roadway for the target stage
c) Discussion of the developed concept with the participation of municipal units: BZM, WIM, WWE, MPWiK S.A. ZdiUM, ZZM and WKS Śląsk Wrocław, followed by adjoining RO Investment together with obtaining a positive opinion of the units of the Municipality of Wrocław, RO and sports club to join the development of:
1.2.3 Construction project
a) Land Development Project
b) Architectural and Construction Design
c) Technical design
1.2.4 Executive draft:
a) Road industry (roadway and parking spaces)
b) Structural industry (bridge over the Lugovina River)
c) Sanitation industry (water supply, sanitation network, rain network)
d) Electrical road lighting
e) Teletechnical industry MKT
f) Teletechnical DIP
g) Traffic engineering industry organization of target traffic
h) Green industry including:
- Dendrological operat together with a stand management project
- Tree conservation project on the site
- Analysis of the possibility of as many plantings as little distance as possible from the sites of tree removal
- Planting design on the basis of aforementioned analysis
i) Small architecture industry
1.2.5. other studies:
a) Geological/geotechnical surveys of the ground
b) Obtaining a decision of a water law permit
c) Enterprise Information Card/Environmental Impact Report
d) The design of securing the existing geodetic carcass
e) Obtaining an environmental decision
f) Obtaining an archaeological decision
g) Subject of works
h) Investor cost estimate
(i) Offer cost estimate
j) Technical Specifications for Performance and Reception of Works
k) Visualization
1.3. Perform of authorial supervision.
The performance of copyright supervision is the primary obligation of the designer as defined in the provision of Article 20 (1) (4) of the Construction Law. Author supervision consists in establishing in progress of construction works compliance with the project, as well as agreeing on the possibility of introducing replacement solutions in relation to those provided for in the project, notified by the construction manager or the supervision inspector of authorial supervision. Number of stays on the construction site in accordance with the IDW annexed to the tender procedure.