Replacement construction of the Steinhavel barrage - Lot 3 "Lock, weir, fish pass and boat drag".
The WNA Berlin is planning to replace the lock, to adapt the outer harbor, to replace the weir, to build a new access road including a crossing structure, to build a fish pass and to build a slope to overcome the gradient for muscle-powered sports boats.
The construction of the project is divided into three lots:
Lot 1: access including culvert structure
Lot 2: outer ports
Lot 3: lock, weir, FAA, boat tow and ancillary systems
The construction of the culvert structure, the access road during the construction period and the associated landscape protection and landscape construction measures (Lot 1) were accepted in September 2020.
The construction of the outer harbors, the recreational craft waiting areas, the bank protection and the associated landscape protection and landscaping measures (lot 2) were awarded in July 2020 and are expected to be completed in May 2021.
The construction of the lock, the weir, the fish pass, the boat drag and the ancillary systems as well as the associated landscape protection and landscaping measures are the subject of this tender document, lot 3.
The lock and the sheet piling of the boat tow will be built in parallel. In order to carry out this work in the planned time frame from 09/2021 to 05/2022, 3 drilling and insertion devices are required in parallel.
The weir can only be erected after the lock has been completed.
Main construction work to be carried out:
General
- technical processing, implementation planning and creation of inventory documents
- Set up, maintain, operate and clear the construction site
- Establish the electrical system
Landscape maintenance work
- preliminary work (construction site clearance)
- vegetation engineering work
- Tree protection
- Protection of species (amphibian protection - length 400 m, deterring breeding birds)
- Collection of large mussels
Manufacture of a fish pass
- approx. 350 m
- approx. 270 m
- deliver approx. 650 t steel sheet piles
- Approx. 5,500 m of loosening and replacement drilling
- approx. 3 350 m
- approx. 970 m
- approx. 630 m
- approx. 42 m
- Manufacture and install 76 precast concrete parts
- approx. 4,500 m
- approx. 2,700 m
- approx. 1,250 m
- approx. 2,370 m
- approx. 650 m
- Manufacture and dismantle approx. 85 t of steel construction pit reinforcement
- close approx. 80 t sheet pile wall valleys (fish passage inside)
- Manufacture and assemble 225 m spar chord (welded)
- Manufacture and install 13 t scraper strips in 2 layers
- Manufacture and assemble approx. 210 m of sliding strips PE-UHMW
- Approx. 21 t of steel access and service walkways, including coating
- Manufacture and assemble approx. 365 m of welded steel railings
- Delivery and assembly of the inlet contactor
- Delivery and assembly of the pillar jib crane (reach 4.0 m / 1.0 t)
- Delivery and assembly of floating beams (stainless steel)
- 2 stop log locks (aluminum) for fish pass
Production of weir systems
- approx. 200 m
- Remove / dispose of hydraulic steel components
- approx. 150 m
- approx. 120 m
- approx. 1,100 m
- Manufacture and install approx. 65 t reinforcing steel for bored piles
- Manufacture approx. 25 t of chords and stiffeners from steel
- Make approx. 36 pressed micropiles (tension pile, 360 kN)
- approx. 400 m
- approx. 200 m
- approx. 660 m
- Install approx. 145 t reinforcing steel bars (B500B)
- approx. 155 pieces of precast concrete parts for sheet pile wall cladding
- 2 pieces of drive unit weir flap (electric lifting cylinder)
- 2 closing flaps weir system (5.5 t)
- approx. 13 t steel construction (fixed parts and bars)
- Manufacture and assemble approx. 65 m of welded steel railings
- approx. 650 m
- approx. 1,500 m
- approx. 670 m
Manufacture of lock systems
- approx. 1,450 m
- Remove / dispose of old lock gates
- approx. 260 m
- Deliver approx. 570 t of steel sheet piles
- approx. 4,800 m loosening and replacement boreholes
- approx. 3,800 m
- Manufacture approx. 70 t of chords and stiffeners from steel
- make approx. 170 pieces of pressed micropile (tension pile)
- Make approx. 14 permanent grout anchors (chamber anchors)
- Make approx. 15 permanent round steel anchors (chamber anchoring)
- approx. 1,000 m
- approx. 400 m
- approx. 1,300 m
- Install approx. 310 t reinforcing steel bars (B500B)
- approx. 440 m
- 8 drive units for lock gates (electric lifting cylinders)
- 2 mitred gates of the lock system (2-leaf)
- approx. 17 t steel construction (fixed parts and bars)
- approx. 58 lock equipment (bollards, ladders, handrails)
- Make approx. 176 m sheet pile wall spar from steel
- approx. 3,500 m
- approx. 4,300 m
- approx. 650 m
Manufacture of boat tow
- approx. 230 m
- Extend the old weir system (free ark)
- Deliver approx. 390 t of steel sheet piles
- Approx. 3,800 m of loosening and replacement boreholes
- approx. 2,700 m
- Make approx. 255 m sheet pile wall spar from steel
- Approx. 105 m of precast concrete parts for boat tow
- temporary weir system (during construction)
Production of company buildings (turnkey)
- Base area 7.40 x 13.10 m
- approx. 100 m
- approx. 175 m
- approx. 160 m
- approx. 280 m
- approx. 180 m
Manufacture of auxiliary systems
- approx. 1,000 m
- 19 foundation piles for crane parking spaces
- approx. 280 m
- approx. 1000 m
- Approx. 500 m of wire mesh fence (height 1.80 m).