The main services to be performed are:
- approx. 500m drainage channels DN100-400 remove and dispose of
- approx. 100m irrigation pipes DN 100 remove and dispose of
- remove and dispose of approx. 15 DN 1000 manholes
- approx. 500 m3 of soil and removal
- approx. 25 pcs of pole-mounted luminaires remove, remove and dispose of
- lay approx. 50 m gas pipeline DN 50 as a temporary solution
- lay approx. 75 m water pipe DN 50 as a temporary solution
- approx. 700 m drainage channels DN 100 laid in ditches
- lay approx. 100 m irrigation pipes DN 100 in trenches
- approx. 2500 m3 of soil BK 2-7 for trenches and shafts
- approx. 500 m3 embedding and overfilling of pipelines
- approx. 3500 m2 shoring to secure the trenches
- install approx. 18 shafts DN 1000
- demolish approx. 2,000 m² of concrete pavement
- approx. 500 m³ earthworks
- ca. 2.700 m³ Schotterarbeiten
- ca. 250 m² Bitukies
- approx. 1,000 m² asphalt
- approx. 300 t natural stone wall, block set
The construction project is a preliminary measure
(Construction phase 0) of construction phase 4 at the Arberlandklinik in Viechtach.
The execution is due to the maintenance of as many as possible
Parking spaces for staff and visitors to the clinic in three
Construction steps, divided as follows:
Construction step 0.1: South side - execution mid-March to end of May 2023
Construction step 0.2: West side - execution from the beginning of June to the end of July 2023
Construction step 0.3: East side - execution beginning of Aug. to end of Sept. 2023
Spartenverlegung:
Essentially, the following civil engineering works will be carried out.
Execution:
- New drainage channels
- New above-ground hydrant incl. water pipe
- Relocation Gas pipe kitchen
- Relocation Cold water main pipe
The work must be carried out during ongoing hospital operations.
Retaining walls:
This section covers the services of the landscape
construction. Here, the southern terrain with demolition and filling work
and the securing of the terrain by walls and the
Construction site access/bypass.