1. The object of the order is:
1) delivery of 5 (five) brand new, low-floor zero-emission electric buses
2) construction of a fast charging station for public transport vehicles on Towarowa Street in Głogów
3) construction of a slow charging station for public transport vehicles on Transporta Street in Głogów
4) providing access to the remote monitoring system of electric bus charging stations, including monitoring at Towarowa Street;
17. A detailed description of the subject of the contract, including the requirements of the Ordering Party, is specified in Annexes No. 1.1, No. 1.2 - to SWZ- Description of the subject of the contract Buses and Description of the subject of the contract Construction of vehicle charging infrastructure and No. 1.3, 1.4 to SWZ - design documentation for fast charging stations at Towarowa Street and slow charging stations at Transport Street.
1. The object of the order is:
1) delivery of 5 (five) brand new, low-floor zero-emission electric buses powered by own energy storage (batteries) intended for operation in regular public transport together with the necessary and additional equipment, software and documentation;
2) construction of a fast charging station for public transport vehicles on Towarowa Street in Głogów, Dz. ewid. No. 146/13 precinct 0001 Nadodrze together with the energy supply infrastructure for the 250 kW charging system – in accordance with the attached design documentation together with the building permit decision;
The scope of works includes, m.in. delivery, assembly and commissioning of a transformer station and 1 (one) fast charging charger with pantograph (inverted pantograph) for buses;
3) construction of a slow charging station for public transport vehicles on Transportu Street in Głogów, Dz. ewid. No. 430/9 precinct 0009 Żarków together with the energy supply infrastructure for the charging system with a capacity of 3 x 80 kW – in accordance with the attached design documentation together with the building permit decision;
The scope of works includes m.in delivery, assembly and commissioning of a transformer station and 3 (three) two-station electric chargers for buses;
4) providing access to the remote monitoring system of electric bus charging stations, including monitoring at Towarowa Street;
A detailed description of the subject of the contract, including the requirements of the Ordering Party, is specified in Annexes No. 1.1, No. 1.2 - to SWZ - Description of the subject of the contract Buses and Description of the subject of the contract Construction of vehicle charging infrastructure and No. 1.3, 1.4 to SWZ - design documentation for fast charging stations at Towarowa Street and slow charging stations at Transport Street. The manner of performing works and the obligations of the Contractor in the scope of construction works are specified in the model contract – Annex 3 to the SWZ.