Attic conversion and conversion of the listed building (built in 1907). The school complex currently comprises 4 full floors. These will be partially renovated in the course of the construction project. The primary school is currently 3-speed and is to be extended by a whole train. The currently unused attic will be expanded accordingly.
The construction measures will be carried out in sections and during ongoing school operations.
Attic conversion and conversion to all-day care of the primary school Heilingbrunnerstraße 3, Bad Reichenhall.
The listed primary school (built in 1907) was supplemented by an extension in 1955. The school complex comprises four fully used floors (UG-2. OG). These will be partially renovated and converted in the course of the construction project. After the ground floor was completed in 2021, the remaining 1st floor, as well as the basement and 2nd floor will be renovated or rebuilt from 2023. The school is to be made barrier-free and will receive an elevator.
The primary school Heilingbrunnerstraße 3 consists of a coherent building, whose parts of the building, however, date from different years.
The entire building complex is a listed building.
The entire building complex is a listed building.
1)Main building (1907) and annex (1955)
- 5-geschossig (UG-2. OG +DG)
-Solid construction, roof wooden construction
-façade length gable side: approx. 25m
-façade length eaves side: approx. 65 m
-Roof type: hipped roof
2)Hipped roof
-Roof pitch approx. 50 ° degrees
-Roof area/m²: approx. 2000 m²
-Ridge height (acc. to OK 0.00): approx. 26 m
-Eaves height (acc. to OK 0.00): approx. 13.5 m
The renovation and conversion work will be carried out during ongoing school operations!
The following dates are planned for the advertised services:
Kran Couples: KW 16 (April 2023 - April 2023)
Roof section 01: CW18-22 (May 2023 - June 2023)
Roof section 02: CW23-27 (June 2023 - July 2023)
Roof section 03: CW28-32 (July 2023 - August 2023)
Roof section 04: CW33-37 (Augst 2023 - September 2023)
Roof section 05: CW39-43 (September 2023 - October 2023)
Other work inside the building (walls, stairs, etc.):
CW 39 - 43 (September 2023 - October 2023)