Renovation of the outdoor swimming pool in Esslingen-Berkheim:
The NRF is about 1 870 m
The following measures are to be implemented in the course of the upcoming refurbishment:
- total renovation of the inner and outer pools (stainless steel lining),
- Renovation of the foyer, changing room and sanitary area,
- complete renewal of the technical building installations (heating, ventilation, sanitary, electric and bathing water technology),
- barrier-free access,
- energetic upgrading of the building envelope.
The work is expected to start in September 2019 - May 2021.
- Excavation excavation - approx. 1 150 m
- Inner wall KS L, d = 11.5 - approx. 550 m
- Facing KS installations 17.5 cm - about 125 m
- Filligrandecke - approx. 320 m
- Columns S1 B / T / H 30/30/710 - approx. 10 St.
- Reinforcing steel finished parts - approx. 17 000 kg,
- Reinforcement connection DN 12 - approx. 220 pieces,
- Interceptor HEB 240 - approx. 5 115 kg,
- Steel supports HEB 140 - approx. 1 400 kg.