The assignment concerns an 'Engineering & Build'. It is noted that study work has already been carried out, so that the 'Engineering' component rather relates to optimizing the already delivered study work that is made available with the underlying specification bundle.
A reference design of the Dilserbos ecoduct was drawn up. The design of the ecoduct, together with the bicycle bridge and the cycle paths, was included in one global environmental permit file. This authorisation is subject to conditions. The assignment includes further drawing up the design of the ecoduct, taking into account the licensed file. The design also includes the calculation of the stability of the entire structure.
The contractor appoints a safety coordinator design and draws up the VGP Design. For the execution, the contractor also appoints a safety coordinator implementation.
An independent inspection agency is appointed by the contractor to monitor the study and the execution of the works.
The contractor is responsible for the execution of the entire design.
The contract mainly comprises:
the study work (engineering) of the subject of this assignment
Ecoduct stability study and accessories
safety coordination design and implementation
the appointment of an independent audit office for the follow-up of the study and its implementation
felling of trees, grubbing up shrubs;
taking less nuisance measures during the execution of the works (over/along/in regional road N75)
making a foundation for the ecoduct making an abutment and middle pillar for the ecoduct
Building the ecoduct
the groundwork for the construction of the integration of the ecoduct into the landscape
the construction of drainage and buffering for rainwater, the local relocation of conflicting sewerage (gravitational drainage)
the study with regard to the vision screen, including the placement of the vision screen on the ecoduct
planting material and seeding works on the ecoduct and in the roadsides
the study and placement of lighting at the bottom of the ecoduct, incorporated into the finishing of the embankments of the abutments
the maintenance of the works during the guarantee period
The assignment concerns an 'Engineering & Build'. It is noted that study work has already been carried out, so that the 'Engineering' component rather relates to optimizing the already delivered study work that is made available with the underlying specification bundle.
A reference design of the Dilserbos ecoduct was drawn up. The design of the ecoduct, together with the bicycle bridge and the cycle paths, was included in one global environmental permit file. This authorisation is subject to conditions. The assignment includes further drawing up the design of the ecoduct, taking into account the licensed file. The design also includes the calculation of the stability of the entire structure.
The contractor appoints a safety coordinator design and draws up the VGP Design. For the execution, the contractor also appoints a safety coordinator implementation.
An independent inspection agency is appointed by the contractor to monitor the study and the execution of the works.
The contractor is responsible for the execution of the entire design.
The contract mainly comprises:
the study work (engineering) of the subject of this assignment
Ecoduct stability study and accessories
safety coordination design and implementation
the appointment of an independent audit office for the follow-up of the study and its implementation
felling of trees, grubbing up shrubs;
taking less nuisance measures during the execution of the works (over/along/in regional road N75)
making a foundation for the ecoduct making an abutment and middle pillar for the ecoduct
Building the ecoduct
the groundwork for the construction of the integration of the ecoduct into the landscape
the construction of drainage and buffering for rainwater, the local relocation of conflicting sewerage (gravitational drainage)
the study with regard to the vision screen, including the placement of the vision screen on the ecoduct
planting material and seeding works on the ecoduct and in the roadsides
the study and placement of lighting at the bottom of the ecoduct, incorporated into the finishing of the embankments of the abutments
the maintenance of the works during the guarantee period