Demolition and new construction of two well structures for the water supply, including installation and process engineering.
Pipeline construction.
Brunnen 3+6 Impfingen.
Demolition and new construction of two well structures for the water supply, including installation and process engineering.
Brunnen 3+6 Impfingen.
2 pcs Well building demolition,
approx. 2000 m3 of earthworks,
approx. 180 m3 Quadermauerwerk
approx. 18 m Winkelstützwand,
1 pc. dewatering,
2 pcs prefabricated well structures,
approx. 85 m2 facing with natural stone,
work on the barrier pipe,
installation of the new well head,
further installation and process engineering.
60 m erdverlegte Druckrohrleitung DN 125 GGG-ZM.