Building automation.
In essence, the following measures are intended for execution:
- Installation of 2 pcs. Control cabinets with freely programmable automation system,
- Connecting new heating circuits on existing control cabinet,
- Number of data points: 250 physical, 350 communicative,
- Control / regulation of heating systems, connection of two independent ventilation systems via BACnet,
- Connecting the automation stations to the existing management system via BACnet IP according to DIN EN ISO 16484-5,
- Setup network for recording the consumption data of 10 meters via M-Bus,
- Construction network for the control of approx. 50 fire dampers,
- Integration of hot water preparation via ModBus,
- Installation of approx. 10,500 m of cable incl. Installation material.