Lot 1.3. Replacement new building FWV-KMR / Fm Curie-Strasse and replacement of Fucik-Strasse with 8 FWA, relocation of GHD and co-relocation of TWV, civil engineering and pipe construction.
Civil engineering services:
1 672 m³ of pipeline trenches; 361 m³ of construction pits, 1 418 m³ of soil disposal / delivery, 3 049 m
Dismantling services:
27 m DH supply lines steel DN 250-400 and 28 m DH supply and connection lines steel DN 50-150 incl. 6 shut-off valves; 148 m GfK-EP-KMR DN 50-80 and 66 m GfK-EP-KMR DN 25-40 supply and connection lines including shut-off valves and molded parts in concrete abutments; 15 m steel pipe DN 25-100 including insulation as well as fittings and connecting pieces, 2 fittings and wall brackets, 25 m steel gas pipes DN 200, 37 m
Pipe construction services: Delivery / laying / assembly of fire-fighting supply and connection lines:
264 m KMR DN 250, 456 m KMR DN 100, 314 m KMR DN 50, 312 m KMR DN 40, 286 pcs.circular welds DN 25-100, 100 pcs.circular welds DN 200-400, 22 pcs.GfK DN joint connections 40-80, 18 underground vents / drains DN 25/50, 20 underground shut-off valves DN 40-50, 4 underground shut-off valves DN 250, 2 underground shut-off valves DN 100, 2 tapping shut-off valves DN 400/100, 120 pcs . KMR elbow DN 40-100, 26 pieces KMR elbow DN 250, 36 pieces KMR prefabricated branches DN 40-100, 10 pcs KMR prefabricated branches DN 250, 340 pcs KMR socket construction Da 110 to Da 200, 90 pieces KMR socket construction Da 280 to Da 560 with expansion padding, IPS wiring and central monitoring device. 59 m steel pipelines DN 15-40 including fittings / connectors, fixings, etc. Insulation from mineral fiber shells, 31 ball valves DN 15-40, 364 round welds DN 15-40.
18 m relocation of high-pressure gas lines DN 200 PN 16 including round welds, fittings and connectors with material provided by the client, coordination of 120 m laying of drinking water pipes DN 150 PE, SiGeKo and measurements.
Planning services:
System-typical FW-KMR statics for the offered product with proof of the expansion upholstery and leakage warning system in an installation and wiring plan; Structural engineering; Traffic sign planning; 8 pieces of work plans of house connections with previous inspections. Statics for transition structure on the heating duct.