The Mörel - Fiesch section represents the second stage of the 380/220/132/65 kV line Mörel - Ulrichen. This is a Swissgrid project. The line runs from the canton of Valais to Ticino and will replace the previous line, which will then be dismantled.
Object of procurement: the 28 mast foundations between Mörel and Fiesch / Ernen are to be rebuilt between spring and autumn 2021. The foundations of the old 220 kV line will be dismantled in autumn 2022 and spring / summer 2023, and the roads used will then be repaired in summer 2023.
Lot 1: foundations for mast 1424-2433 (with micro piles).
Lot 2: foundations of mast 2434-2443 (with micro piles).
Lot 3: foundations for mast 1443-1450 (with micro piles).