A central processing unit for medical devices (AEMP) is to be set up in the building of the former central kitchen on the Berg Clinic.
The essential requirements for the performance "Technical insulation" can be found under point s. II.2.4).
- 800 running meters of condensation water insulation on SML pipe;
- 2,000 running meters of rock wool insulation heating pipe according to EnEV;
- 1 100 running meters of rubber insulation on a cold water pipe according to EnEV;
- 1 400 m
- 1 200 m
- 80 pipe seals for heating pipes;
- 30 pieces of pipe insulation for cold pipes;
- 60 pieces of fire insulation electric.