Tender for construction contracts consisting of excavation, under-drilling, cable laying and restoration of affected areas in connection with the establishment of
Lot 1: 132 kV excavation and cable laying contract "Fehmarn" consisting of the sections:
Fehmarn-Rødby
Fehmarn-Gloslunde
Lot 2: 132 kV excavation and cable laying contract "Lolland" consisting of the sections:
Gloslunde – West Lolland
Rødby rearrangement
Excavation and cable laying contract, 132 kV Fehmarn (Fehmarnbelt Rødby + Fehmarnbelt Gloslunde)Subpart 1:
132 kV excavation and cable laying contract Fehmarn consisting of the sections:
Fehmarn-Rødby
Fehmarn-Gloslunde
The scope of the work is described in the tender documents and includes, inter alia,(the list is not exhaustive):
• Detailed design of the contract
• Applications for necessary crossing agreements and digging permits
• Establishment and operation of shanty town(s)
• Earthworks related to the establishment of cable pits, sleeve pits, link boxes,
fibre boxes etc. as well as subsequent restoration – including any
oplagringspladser along traceet
• Works in connection with the preparation of cable pulling places
• All transportation and delivery costs in connection with this service above
• Delivery, handling and coordination of driving plates
• Delivery of all necessary equipment for cable pulling
• Execution of sub-drilling in the tracé and the associated earthworks, excl.
land underboring (HDD)
• Carrying out pipe laying in the tracée, if necessary
• Pulling high voltage cables
• Pulling pipes for fiber cables
• Ibblasting fiber cables
• Bentonite filling of all sub-drilling pipes and pipes in open pit.
• Restoration of intersecting and longitudinal drains in the trail
• Handling and/or protection of intersecting wires and piping.
• Supply and establishment of wells for the assembly of fiber cables and link boxes
• Earthworks in connection with the establishment of earthing installations in the sleeve pits, as well as
establishment and documentation of the earthing plant;
• Installation of marking posts provided by the client
• Image or video documentation of private and public roads used for
work run before work starts and after finishing work;
For the tendered contract, large parts of the covered tracé are located below sea level, and many drainage channels and many drains are to be expected.
Digging and cable laying contract, 132 kV Lolland (Gloslunde - West Lolland + Rødby conversion)Subpart 2:
132 kV excavation contract Lolland consisting of the sections:
Gloslunde – West Lolland
Rødby rearrangement
The scope of the work is described in the tender documents and includes, inter alia,(the list is not exhaustive):
• Detailed design of the contract
• Applications for necessary crossing agreements and digging permits
• Establishment and operation of shanty town(s)
• Earthworks related to the establishment of cable pits, sleeve pits, link boxes,
fibre boxes etc. as well as subsequent restoration – including any
oplagringspladser along traceet
• Works in connection with the preparation of cable pulling places
• Delivery, handling and coordination of driving plates
• Delivery of all necessary equipment for cable pulling
• Execution of sub-drilling in the tracé and the associated earthworks, excl.
land underboring (HDD)
• Carrying out pipe laying in the tracée, if necessary
• Pulling high voltage cables
• Pulling pipes for fiber cables
• Ibblasting fiber cables
• Bentonite filling of all sub-drilling pipes and pipes in open pit.
• Restoration of intersecting and longitudinal drains in the trail
• Handling and/or protection of intersecting wires and piping.
• Supply and establishment of wells for the assembly of fiber cables and link boxes
• Earthworks in connection with the establishment of earthing installations in the sleeve pits, as well as
establishment and documentation of the earthing plant;
• Installation of marking posts provided by the client
• Image or video documentation of private and public roads used for
work run before work starts and after finishing work;
For the tendered contract, large parts of the covered tracé are located below sea level, and many drainage channels and many drains are to be expected.