The subject of the tender are track, underground and road construction services for the barrier-free expansion of the section from the Palatinate Center to the cemetery in Leimen as well as a 90 m long track renewal directly north of it.
In addition to 5 platforms and 2 bus platforms, the entire street area with lane, parking, sidewalk, bicycle traffic and green spaces will be renewed. The empty pipe infrastructure must be established for telecommunications lines.
- Dismantling of the existing track systems (construction area 4 only) and stops;
- dismantling the existing traffic areas (roadway, sidewalk);
- earthworks in the area of the new traffic areas;
- New construction of track systems for light rail vehicles :;
- Slab track (RhedaCity system) with asphalt, paving and lawn covering;
- Opening and restoring the surface for placing overhead line masts (the positioning is done by third parties on behalf of the AG);
- Manufacture of 5 platforms (Stadtbahn) and 2 bus platforms including empty pipe infrastructure and guard rails;
- Manufacture of empty pipe infrastructure including inspection shafts for telecommunications lines from Rhein-Neckar-Verkehr GmbH, the city of Leimen (light signaling technology) and the ZV high-speed network Rhein-Neckar;
- Manufacture of cable trenches and protective pipes for connection lines for street lighting and supply lines from Syna GmbH (electricity);
- Renewal / adaptation of the street and track drainage including the associated connection pipes;
- New traffic areas for individual traffic;
- pavement and asphalt roadways;
- Parking areas, sidewalks / bike paths with concrete pavement;
- Manufacture of a covered bicycle storage facility;
- Manufacture of foundations for the station equipment;
- Installation, provision, implementation of signs for traffic management during construction and site security;
- making green spaces;
- Application of the final lane marking and application of the final signage.
Composition of the main masses:
Dismantling:
- approx. 400 m tracks;
- 2 grooved rail switches;
- approx. 2 700 m
- approx. 6 400 m
- approx. 1 400 m edge stones.
new building:
- approx. 1,200 m of track (slab track);
- 2 grooved rail switches;
- approx. 5 700 m
- approx. 4 150 m
- approx. 185 m platform edges;
- approx. 2,000 m edge stones;
- approx. 60 street drainage shafts;
- approx. 600 m empty pipe route (route length);
- approx. 80 cable ducts.