Redesign of the streets, paths and squares at the Tribseer Damm junction Carl-Heydemann-Ring. The measure is carried out together with the REWA mbH pension provider. The provisional net construction costs for street lighting are approximately EUR 46,000 net.
Appointment chain:
Development of implementation planning (LPH 5) by October 15, 2020 at the latest; Preparation of award (LPH 6) by October 30, 2020; Start of construction February / March 2021 (construction time approx. One year). The deadlines must be met.
By submitting your offer, you declare that you can perform the services within the specified time frame.
The subject of the service to be provided is - Technical equipment of system group 4 for LPH 5-9 (§§ 55 of the HOAI) acc. Appendix 15.2.