The school complex in Wittelsbacher Straße in Germering will be energetically renovated and expanded in several construction phases.
First, the extension for the primary school was completed. At the same time, two gymnasiums and a building wing for
Lunchtime care – care bridge – newly built. Currently, the middle school is being completely renovated, expanded and increased. Between
of the Middle School and gymnasiums, a break hall covered with a wooden roof is being built.
In the course of this, new furniture is to be supplied for the following rooms:
• Science room with adjoining rooms
• Art room with adjoining room
• WTG room with adjoining room
• 2 x Informatikraum
• First aid room
• 5 x multifunctional central zones
In addition, the following furniture is to be added:
• Teachers' tables – 2 pcs.
• Teachers' room tables – 4 pcs.
• Folding tables – 15 pcs. with transport trolley
• Stackable tables – 8 pcs.
• Chairs teacher – 15 pcs.
• Chairs pupils – 24 pcs.
• Hook strips / mobile wardrobe trolleys – 23 pcs.
• Cabinets – 5 pcs.
• Sideboards – 4 pcs.
• Shelves – 9 pcs.
Events:
Publication of procurement documents: 19.08.2022
Voting, release, order: 24.10.2022-11.11.2022
Assembly start: 06.02.2023
Completion of furniture assembly: 17.02.2023