The orthopaedic building complex built at the beginning of the 30s in Semmelweis-/Philipp-Rosenthal-Straße, which has already been renovated and unused several times, for the last time as a psychiatry, is again in need of renovation. A core task is the complete replacement of the ailing drinking water system, including connection to the public utilities, as well as the upgrading of the low-voltage grid, especially in the telecommunications sector. In addition, there are mandatory interventions in the main building distribution to ensure operation.
Drinking water remediation takes place in the clinical areas. Staff changing rooms, ward bathrooms and bathrooms in the patient rooms will be converted. The adjacent floor surfaces concerned will receive new linoleum coverings.
The services take place in a predefined order of the floors.
3,500 m2 demolition of old coverings in sections
The sub-surfaces coverings include:
SG......... 650 m2
EG........ 1.300 m2
1.OG.... 500 m2
2.OG... 650 m2
3.OG... 400 m2
1.400 m2 Linoleumbelag
2,000 m2 PUR flooring
100 m2 PVC flooring
52 m2 Sportboden + Linoleumbelag
Groutings, recesses