This assignment includes in particular:
- performing topographical operations
- demolition of fences
- sheeting trees and grubbing hedges and thickets
- breaking up existing pavements and their foundations
- demolition of sewers with associated inspection wells
- demolition of homes
- installation of DWA and RWA sewers: ND300 - ND1200; depth 1.20 to 3.75 m; length ± 2,515 m
- installation of buffer pipes concrete d700 + d1200
- building inspection wells
- building squeeze-overflow constructions/ thresholds/ headwalls
- building 1 overflows
- earthworks on the earth
- construction of subfoundations and foundations
- installation of gutters and curbstones
- installation of street swirls and their connections
- construction of roadway pavements of concrete, asphalt concrete and concrete pavers
- realising connections of domestic sewers
- pavement of footpaths
- site signaling
- signaling of redirects
- Definitive road signs
- cleaning, cleaning and all necessary operations to bring the works into a state of completion
- Landscaping and maintenance
- Maintenance of works during the guarantee period.
The contract consists of one lot.