KAS kodit Oy shall request your offer for a total contract in accordance with this invitation to tender and the accompanying documents. KAS kodit Oy is responsible for the construction tasks of the project.
KAS, the total contract, Nummela acquisition aims, using an open procedure, to acquire a whole-female economically advantageous builder for the use of the subscriber who is best placed to build the item in this tender.
KAS kodit Oy is building a lift, two-tier, five-story residential apartment building at Kappelitie 6 (927-436-1-324) in Vihdi Nummela. There are 56 housing units. There are 56 car spaces, and they are located on the south-east side of the plot, on the ground. Two car locations are equipped with electric car charging points supplied by a separate supplier. The target's population shelter is located on the A-stair, on the 1st floor. The ride to the property is from Kappelroad, east of the plot.
Scope of construction object
Number of residential buildings 1 piece
Layer number 5 layers
Stairrooms, pcs 2
Lifts, pcs 2
Number of dwellings, pcs 56
Apartment area 2544.5 m2
Construction right used 3500 kem²
Gross area, total area 3855,75 m²
Volume (gross) 12609.5 m³
Plot area 4310,5 m2
The subscriber has received a conditional funding decision for the project from the Housing Finance and Development Centre (hereinafter referred to as “ARA”). The object is carried out on a plot owned by the developer. The plot has a reinforced station formula. The project has a butter-mass construction permit.
The project is ARA-Contingent. The project will be carried out and construction work on the site may be started after ARA issued a positive partial decision for the project, as well as a starting permit.
We ask you for an offer for a total contract to complete and complete the work under the documents attached to the tender. We ask you to submit your offer with annexes to the SokoPro Project Bank no later than 1 March 2022 at 10:00 a.m.
The starting point for the selection of contractors is the economic and high-quality implementation of the project. Uraka's main task is to implement the project according to the subscriber's plans, in accordance with the cost level approved by the ARA.
The main goals of the subscriber for construction are:
- Destination is reasonably priced (ARA destination)
- The object is carried out according to plan and is appropriate at quality level
- Cooperation during the project is smooth and communication is proactive among the project parties
- The principles of Dry Chain10 are applied in the project.
- The planned start date of construction is 6/2022—10/2023. A total of 15 months has been allocated for construction time.
Plans for the project have mainly been drawn up during 2021. The project is designed using the data model. During construction, you can take advantage of the data model during construction.
KAS kodit Oy shall request your offer for a total contract in accordance with this invitation to tender and the accompanying documents. KAS kodit Oy is responsible for the construction tasks of the project.
KAS, the total contract, Nummela acquisition aims, using an open procedure, to acquire a whole-female economically advantageous builder for the use of the subscriber who is best placed to build the item in this tender.
KAS kodit Oy is building a lift, two-tier, five-story residential apartment building at Kappelitie 6 (927-436-1-324) in Vihdi Nummela. There are 56 housing units. There are 56 car spaces, and they are located on the south-east side of the plot, on the ground. Two car locations are equipped with electric car charging points supplied by a separate supplier. The target's population shelter is located on the A-stair, on the 1st floor. The ride to the property is from Kappelroad, east of the plot.
Scope of construction object
Number of residential buildings 1 piece
Layer number 5 layers
Stairrooms, pcs 2
Lifts, pcs 2
Number of dwellings, pcs 56
Apartment area 2544.5 m2
Construction right used 3500 kem²
Gross area, total area 3855,75 m²
Volume (gross) 12609.5 m³
Plot area 4310,5 m2
The subscriber has received a conditional funding decision for the project from the Housing Finance and Development Centre (hereinafter referred to as “ARA”). The object is carried out on a plot owned by the developer. The plot has a reinforced station formula. The project has a butter-mass construction permit.
The project is ARA-Contingent. The project will be carried out and construction work on the site may be started after ARA issued a positive partial decision for the project, as well as a starting permit.
We ask you for an offer for a total contract to complete and complete the work under the documents attached to the tender. We ask you to submit your offer with annexes to the SokoPro Project Bank no later than 1 March 2022 at 10:00 a.m.
The starting point for the selection of contractors is the economic and high-quality implementation of the project. Uraka's main task is to implement the project according to the subscriber's plans, in accordance with the cost level approved by the ARA.
The main goals of the subscriber for construction are:
- Destination is reasonably priced (ARA destination)
- The object is carried out according to plan and is appropriate at quality level
- Cooperation during the project is smooth and communication is proactive among the project parties
- The principles of Dry Chain10 are applied in the project.
- The planned start date of construction is 6/2022—10/2023. A total of 15 months has been allocated for construction time.
Plans for the project have mainly been drawn up during 2021. The project is designed using the data model. During construction, you can take advantage of the data model during construction.