Contract Value:
-
Notice Type:
Contract Notice
Published Date:
17 June 2022
Closing Date:
15 July 2022
Location(s):
BE332 Arr. Liège (BE Belgium/BELGIQUE-BELGIË)
Description:
RETROFIT OF THE IVOZ-RAMET HYDROELECTRIC POWER PLANT

Primary scope: Retrofit of the Run-Off-River Hydro Power Plant which is dated from 1952 equiped with 3 vertical Kaplan turbines of 3,3MW each. Retrofit is planned to start in 2023.

Secondary scope: Retrofit of the generators.


Retrofit of the turbines and associated auxiliaries

Lot 1:

- The retrofit of 2 out of 3 turbines and optionally the third one.

- The replacement of the oil governor and implementation of digital governor

- The supply and installation of the turbine control & protection system including local HMI

- The supply and installation of a low voltage cabinet for the turbines auxiliaries consumers

- The supply of the associated mechanical and electrical auxiliaries, accessories, and instrumentations


Refurbishment of the generators and associated auxiliaries

Lot 2:

- The lifetime extension works of 2 out of 3 generators and optionally the third one

- The retrofit of the excitation system

- The retrofit of the generator’s control & protection system including local HMI

- The supply of the associated mechanical and electrical auxiliaries, accessories and instrumentations

Download full details as .pdf
The Buyer:
Luminus
CPV Code(s):
31124100 - Turbine generator sets
45315200 - Turbine works
71300000 - Engineering services