For the city of Nierstein, a need for 40 more kindergarten places was recognized. Since there are no possibilities for expansion in any current municipal day care center, a new building is necessary.
The concept of the new day care center should be designed in such a way that an extension of the new building by at least 2 groups would be possible in principle, both in terms of building and supporting structure as well as with regard to the technical equipment.
Legal requirements for sustainability and energy saving during construction and operation must be observed. Economic solutions must be planned and savings opportunities identified. The aim is to achieve savings and to fall below the costs involved.
The following plots are planned for the construction project: parcel 478 (approx. 4,689 m²) and possibly 20/3 (approx. 675 m²) in Hoffmann-von-Fallersleben-Straße in 55283 Nierstein.
The property is located within the territorial scope of the legally binding development plan "Roßberg-West II, 4th BA with 1st amendment and supplement". The determination under building planning law according to § 9 Abs. 1 Nr. 15 BauGB is "Public green space" with the purpose of "green area/play area". The development plan must be amended in an accelerated procedure according to § 13a BauGB in accordance with the specifications of the object planning.
Planning services of technical equipment AG 1 - Sewage, water and gas systems, AG 2 - Heat supply systems, AG 3 - Ventilation systems, AG 7 - use-specific systems Facilities, AG 8 - Building carThe subject of this lot 1 is the planning services of the technical equipment in the service phases 1-9 according to § 55 HOAI, AG 1, 2 and 3, as well as special services.
The estimated costs of cost groups 400 are:
— Anlagengruppen 1: 72.605 EUR,
— Anlagengruppen 2: 108.907 EUR,
— Anlagengruppen 3: 84.706 EUR,
— Anlagengruppen 7: 78.655 EUR
— Anlagengruppen 8: 27.227 EUR.
The awarding body intends to award these planning services in stages. In service level 1, service phases 1 to 4 according to HOAI 2021 as well as the special services required in these phases are to be commissioned.
In service level 2, the awarding body intends to award service phases 5 to 9 according to HOAI 2021 as well as the special services required in these phases.
Planning services of technical equipment AG 4 - Heavy current installations, AG 5 - Telecommunications and information technology Installations, AG 8 - Building automation systemsThe subject of this lot 2 is the planning services of the technical equipment in the service phases 1-9 according to § 55 HOAI, AG 4, 5, 7 and 8, as well as special services.
The estimated costs of cost groups 400 are:
— Anlagengruppen 4: 169.411 EUR,
— Anlagengruppen 5: 36.304 EUR,
— Anlagengruppen 8: 27.227 EUR.
The awarding body intends to award these planning services in stages. In service level 1, service phases 1 to 4 according to HOAI 2021 as well as the special services required in these phases are to be commissioned.
In service level 2, the awarding body intends to award service phases 5 to 9 according to HOAI 2021 as well as the special services required in these phases.
Structural engineering servicesThe subject of this lot 3 is the planning services of structural design in service phases 1-9 according to § 55 HOAI.
The estimated costs of cost group 300 are EUR 1,159,664 (net) and those of cost group 400 are EUR 605,042 (net).
The awarding body intends to award these planning services in stages. In service level 1, service phases 1 to 4 according to HOAI 2021 as well as the special services required in these phases are to be commissioned.
In service level 2, the awarding body intends to award service phases 5 and 6 according to HOAI 2021 as well as the special services required in these phases.