Landschaftsbauarbeiten
The bill of quantities includes the redesign and redesign of the schoolyard area of the Ackermann and Mayor Grimm School in Frankfurt am Main.
Dimensions (approx.):
820 m Loosening, removing curbs
Loosen and dispose of 1,120 m² of pavement
Loosen and dispose of 230 m² of slab flooring
Loosen and dispose of 480 t of bituminous pavement
1,165 m² tartan surface, 2cm, loosen, dispose of
Loosen and dispose of 35 m² EPDM fall protection tiles
Dissolve and dispose of 290 t of bituminous drainage asphalt
28 m² staircase, concrete, loosen, dispose of
60 m Loosen drainage channel Dispose of
19 pcs Loosen furniture, dispose of it
2 pcs Break off equipment sheds, dispose of them
180 m Loosen concrete base / wall angle, dispose of
Different tree protection measures during construction
Create 43 m² root bridges
120 m² improvement of tree sites, overbuilt/not overbuilt
Loosen 180 m³ topsoil
845 m³ Loosening the underbody
Loosen 490 m³ underbody (optional / additional)
Dispose of 530 t of soil (BM-F1)
Dispose of 260 t of soil (optional / additional)
Dispose of 1,120 t of soil (> BM-F3)
Dispose of 620 t of soil (optional / additional)
1,900 m³ of mineral fillings
Dispose of 1,035 t mineral mixture (BM-F1)
Dispose of 1,506 t of mineral mixture (> BM -F3
290 m of pipeline trenches
30 m of electric trenches
290 m of drainage pipes
50 m drainage channel, cast grate cover, make
Making 21 m slotted gutters
Install 20 pcs courtyard inlets
580 m of installing curbs
Installing 3,080 m² of pavement
Install 100 m trough stone
Making a 31 m² pavement trough gutter
Laying 80 m² of small paving
1,045 m runner layer Pavement edging
Laying 70 m² lawn liner
Produce 730 m² of asphalt surfaces
Producing 456 m² of EPDM coverings
Laying 250 m² of concrete slabs
725 m Linierungsarbeiten
Create and dispose of 325 m² of temporary access roads
115 m³ Fallschutz Holzhäcksel
1 pc jump pit making long jump
Make 70 m block steps/stairs
Produce 24 m steel edges as ramp edging
80 t Natursteinsitzblöcke
1 pc making swing forest
1 St Balancieranlage klein
1 St Balancierparcour
15 pcs Seating platforms, wood
2 pcs dwelling platforms, wood
1 pc calisthenic system
6 St Sitzkonstruktionen
2 St Multisportanlagen
27 pcs bike racks and scooter parkers
6 St Picknickkombination
2 pcs rearrange / set up material container
Cultivate 1,600 m² of vegetation
10 pcs Tree plantings, standard trunk
400 St Gehölzpflanzungen
180 m³ tree pit 'Stockholm System'
1 year of F-care + 1 year of E-care
The construction period will take place in at least 4 construction phases:
1.BA: 1st/2nd week 2024 to 16.02.2023,
BA 2 - BA 4: until December 2024,
BA 3: during the Hessian Easter holidays 2024,
End of construction of all construction phases expected at the end of December 2024 / January 2025.