Shielding and earthworks (see brief description of the lot)
Asbestos removal: - removal of façade plates containing asbestos: 1 fft Earthworks: - Mechanical earthworks in full mass in class 3-5 land and evacuation: 4,100 m3 - mechanical earthworks in full mass in class 6 or 6-7 crumbled rock and evacuation: 700 m3 - mechanical earthworks in full mass in class 7 compact rock and evacuation: 3,600 m3 - Mechanical earthworks for boreholes in class 3 to 5 terrain or compact embankments and drainage: 60 m3 - Mechanical earthworks in trenches in the sidewalks for shaft clearance and drainage: 550 m3 Shielding: - supply and installation of metal studs and sealing in perforated holes: 80,000 kg - supply and installation by gunning of a C20/25 smooth float concrete on the metal profiles: 500 m2 - BST steel 500 m (A) in welded mesh for the gunning reinforcement: 6,500 kg - temporary anchor tie rods with a payload of 150 A 400 KN: 65 pcs Start of work: 10.05.2024 Duration of the works: 110 days according to schedule attached to this file