Refurbishment and conversion of Herderhaus to the city archive, lot 25-1, interior insulation work, 1st construction phase
Internal insulation calcium silicate, surface treatment pore base plaster, light plaster on insulation.
Scope:
Internal insulation calcium silicate:
- 1 400 m 2nd on outer walls;
- 320 m 2nd on the underside of the ceiling;
- 545 m 2nd in window / door reveal;
- 105 m 2nd under window sills.
Substrate preparation:
- 2 900 m 2nd Pore base plaster according to WTA as a base for insulation;
- 100 m 2nd Spraying on new masonry;
- 110 m 2nd Pre-treatment of concrete walls.
Plaster:
- 280 m 2nd Light plaster on the insulation of the underside of the ceiling;
- 280 m 2nd Light plaster on insulation in window / door reveals.