Kabeltiefbau ESTWs
Dismantle and dispose of concrete feet (small and large design) approx. 33 pcs
Expand U-channels of various sizes approx. 300 m
Creation of edge paths incl. embankment, W = 80 cm, D = 10 cm approx. 1,800 m
Backfilling of Randweg building material mixture 0/32 from natural GK approx. 750 m³
Supplying and installing cable ducts of various sizes approx. 1,725 m
Cable ducts of different sizes regulate height and position approx. 2,000 m
Shaft connection kits of various sizes approx. 80 pcs
Cable ducts size IV supply and manufacture approx. 75 pcs
Supply and install cable conduits 2xDN110 under the tracks incl. concrete sheathing approx. 275 m
Best. Cleaning and calibrating pipe routes and crossings approx. 1,500 m
Best. Opening and cleaning sewer shafts approx. 60 pcs
Production of a ballast bracket consisting of old rail profiles of the AG each 2.0 m and concrete infill approx. 1,450 m
Making pile pipe foundations of various depths approx. 36 pcs
Produce asphalt base course d = 20 cm in track crossings approx. 55 m²
Supply and install paving of various formats approx. 150 m²
Concrete base monoblock system supply and installation approx. 16 pcs