Strand renovation including renewal of distribution lines in the basement
Disassembly gas pipe
Ventilation technology works
Extended shell construction: bricklaying; concrete work in the shafts
screed plastering
drywall
Tiles
joiner
Painting and flooring work
Metallbauarbeiten
Selective work on the roof
Strand rehabilitation services
(Work in the apartments (222pcs) and the commercial storage (14pcs))
10 to 12 storey building, with 5 entrances, in solid mixed construction (stb+MW) with commercial underlay on the ground floor; full basement, flat roof (warm roof) renovation is carried out in a partially inhabited condition. The continued operation of the subordinate commercial area must be ensured over the entire construction period.
Electrical Engineering:
Strand remediation
Construction of meter centralizations for 222 meter spaces in the basement, new risers by apartment (approx. 12,000 m), installation of fire protection ducts in necessary corridors (approx. 1,200 m), partly Renewal of e-installation in kitchen/bath/WC, 222 WE distributor according to the state of the art.
Installations of new meter centralizations for commercial units, new risers and sub-distributions in the trades, repair measures on plant components in the respective trade
Safety lighting:
Emergency lighting is to be installed in the stairwells, cellar corridors, elevator anterooms and those on the escape balconies. There are approximately 470 LED safety lights/escape sign lights to be installed. The cables are routed in sheet metal ducts (approx. 600m) in the respective safety lighting section. The feeder (approx. 2,000 m) is set up to maintain its functionality. Every staircase receives an emergency lighting center.
Trade building services:
Sanitary engineering:
Line renovation including renewal of distribution lines in stainless steel system pipe with press fittings approx. 2500 m, residential distribution pipe in plastic composite pipe approx. 1200 m, renovation of equipment in 75 units with tubs or showers, dirty water in sound-insulated plastic pipe approx. 700 m and floor in HT pipe approx. 450 m, rainwater from SML pipe approx. 460 m with connecting clamps
Heating technology:
Line renovation including renewal of distribution lines in the basement in stainless steel system pipe with press fittings approx. 5000 m. Renewal of bathroom radiators and replacement of all thermostatic valves and return fittings, 1200 HK
Gas:
Disassembly of gas pipes (1,100 m) and meters approx. 190 pcs.
Ventilation technology:
Renewal of the strings in a calcium-silicate duct with fire containment in the strand outlet, spiral seam pipe with fire containment in the floor ceiling and constant exhaust air valves, central exhaust fans on the roof
Building construction trade:
Central construction site facility:
Construction of containers, construction fence (approx. 450m), construction of the BE
Scaffolding of 5 scaffolding towers including elevators (approx. 1650 sqm)
Extended shell construction: bricklaying; concrete work in the shafts (bulkheads); core drilling (650 pcs)
Screed (approx. 80 square meters), plaster work
Drywall (wall/shaft (approx. 2100 sqm) and suspended ceiling constructions (approx. 1850 sqm)
tiles (floor approx. 1130qm- and wall tiles ca 2700qm),
carpenter (222WE doors + work on interior doors),
painting. (5100sqm wall and ceiling) and floor covering work (2000qm)
Metalwork (fire doors and aluminium systems for escape stairwells)
Building cleaning 222 WE, 5 building entrances; site equipment container+consumables
Selective work on the roof in the course of strand renovation
Renewal of canopies above the trade (1st floor)
Work in the trade in connection with strand renovation (analogous to residential services)