Replacement of the Rottendorfer Straße bridge due to the existing defects in the structure. In addition, the bridge no longer meets the requirements in terms of load-bearing capacity and usable widths of the associated traffic routes.
Replacement of the Rottendorfer Straße bridge:
- Approx. 1,720 m3 of reinforced concrete demolition
- Approx. 450 m bored piles d= 90 for dissolved bored pile wall
- Approx. 650 m of bored piles d = 90 reinforced for overlapping bored pile wall
- Approx. 820 m bored piles d= 90 for overlapping bored pile wall unreinforced
- Approx. 1090 m Micropiles
- Ca. 107 to Pfahlbewehrung
- Approx. 5,910 m3 of excavated soil on interim storage
- Deliver + install approx. 1,650 m3 of reinforced concrete
- Deliver + install approx. 76 m3 of cap concrete
- Deliver and install approx. 276 tons of reinforcing steel
- Ca. 5.000 m3 Bauwerkshinterfüllung
- Approx. 16 tons of steel for bridge construction
- Supply + install approx. 4,000 m2 of asphalt for road construction