The subject of this award procedure is the delivery, construction and commissioning of a hydrogen refuelling station as well as the supply of green hydrogen and the maintenance of the refuelling station after commissioning for the refuelling of initially 10 hydrogen buses.
The delivery and commissioning of the hydrogen filling station must take place by 31.12.2025 due to the requirements of the funding decision of the funding body, otherwise there is a risk that the subsidies will be cancelled.
It should be noted that all communication about the project process is in German language and writing. This means that the requests to participate and the offers as well as all annexes, evidence, declarations, etc. must be written in German.
The subject of this procurement is the delivery, construction and commissioning of a hydrogen refuelling station as well as the supply of green hydrogen and the maintenance of the refuelling station after commissioning for the refuelling of initially 10 hydrogen buses.
The delivery and commissioning of the hydrogen filling station must take place by 31.12.2025 due to the requirements of the grant decision, otherwise there is a risk that the subsidies will be cancelled. The complete delivery and acceptance of the filling station must be guaranteed within the specified period within the scope of the submission of the offer.