Description:
A 4, ERN Beton-FB, km 114.1 - 123.0 b. FR, Lot 2: Road construction, structures, drainage

A 4, ERN Beton-FB, km 114.1 - 123.0 b. FR, Lot 2: Road construction, structures, drainage

The overall construction project includes the renewal of both lanes of the A 4 motorway between km 114.1 and 123.0 as well as the renewal of the Schmölln junction.

Lot 2: Track construction includes: km 113.37 to km 123.00 RF Aachen, km 114.10 to km 123.00 RF Görlitz, dismantling of vehicle restraint systems, structures, renewal of the Schmölln junction, renewal of the passage lane of the Altenburger Land service station, renewal of the bituminous superstructure of the L 1361 at the Schmölln junction.

The construction project is divided into several construction phases. The bill of quantities is divided into the areas of RF Görlitz (with AS Schmölln and T+R Altenburger Land) and RF Aachen (with AS Schmölln and T+R Altenburger Land). Other areas include the production of the median strips and backfills, measures on rainwater retention basins and the dismantling of vehicle restraint systems.

The construction sites are

- BAB 4, Görlitz carriageway, km 123.00 to km 114.10 version 2023/24

- BAB 4, Aachen carriageway, km 113.37 to km 123.00 version 2024/25

The planned construction project includes the following main

Main construction services for the construction of the line:

- Advance services for the repair of the RF Aachen

- early (i.e. before the establishment of the 4+0 traffic routing) services at central and dividing strip crossings: o Upgrading of the median strip crossing 113.15 o Construction of 3 additional temporary median strip crossings

- Dismantling of existing vehicle restraint systems in the construction sector

- Renewal of the superstructure in concrete or asphalt construction

- Renewal of the ramp lanes (bound and unbound superstructure) of the AS Schmölln (61)

- Renewal of existing median strip crossings

- partial renewal of drainage systems

- Renewal of the on-board equipment and paving surfaces (in natural stone/granite)

- Renewal of the previous. Flow

- Rehabilitation (renewal of surface and binder course) of the Altenburger Land petrol station and rest area

- Rehabilitation (renewal of surface and binder course) of the L 1361 in the area of the Schmölln junction

- Restoration of median strip including backfilling BSW

- Renewal of basin bypasses and small capacities for 6 rainwater retention basins

- Renewal of emergency telephone locations

- Restoration / adaptation of induction loops in the construction sector

- Marking as end marking

- Renewal of the standard signage

The following services are to be provided on buildings:

- Earthworks and paving work (canopy connections, embankments, WL berms, service routes, spandrel areas, existing shafts, replacement and extension of existing curbs)

- Concrete repair on substructures, superstructures and caps

- Repair work on existing service stairs and construction of new service stairs, exposure of existing service stairs from vegetation

- Repair of individual joint tapes

- Partial repair and addition of joints on paved surfaces or troughs \u2012 Partial corrosion protection and other repair of steel construction (superstructure beam)

- Partial corrosion protection on T90 profiles \u2012 Repair of existing ÜKO's (replacement of wear parts/sealing profiles, corrosion protection, cleaning)

- Partial renewal or partial corrosion protection and other repair of railings

- Addition of splash guards on cap railings

- Addition of railings on service stairs

- Repair of BW drainage (pipe outlets and bridge drain tops)

- Renewal or repair and relocation FRS

- Gradient compensation (Sprottetalbrücke RF Görlitz)

- Dismantling and renewing the protective layer and waterproofing as part of the production of the compensating gradient (Sprottetalbrücke RF Görlitz)

- Check the protective layer and waterproofing and, if necessary, partially repair it (A-structures and Sprottetalbrücke RF Aachen)

- Addition of wildlife protection fences

- GRUBBING

- Renewal of VZB, cantilever beams, side stands including foundations

Gross amounts:

- approx. 250,000 m² of roadway concrete demolition and new construction

- approx. 270,000 m² asphalt base course under concrete

- approx. 95,000 m³ Frostschutzschicht

- approx. 8,600 m renewal of partial and full seepage pipe DN 150 - demolition and new construction

- approx. 37,000 m² asphalt base and asphalt binder course - demolition and new construction

- approx. 21,000 m² mastic asphalt surface - demolition and new construction

- approx. 18,000 m banquets - demolition and new construction

- approx. 18,000 m dismantling FRS concrete

- approx. 8,500 m FRS dismantling steel

- approx. 55,000 m marking

Download full details as .pdf
The Buyer:
Die Autobahn GmbH des Bundes - NL Ost
CPV Code(s):
45232452 - Drainage works
45233110 - Motorway construction works
45233124 - Trunk road construction work