ETICS and painting work for the 1st BA
Brief description of the measure:
In addition to the existing main building, a 3-storey new building for a primary school is to be built on the site of IGS Lindenfeld. The construction project will be carried out in 2 construction phases. The benefit described here concerns the 1.BA. The building will be constructed in solid construction.
For further descriptions, see specifications
Execution times:
Technical clarification, sample: within 4 weeks after placing the order
Plastering and painting work, in advance technical rooms 31.07. - 19.08.2023
ETICS, in advance, transformer room inside 31.07. - 19.08.2023
Graffiti protection inside, corridor walls 1st page: 04.09. - 29.09.2023
Under- and top-mounted, graffiti protection in the area of radiators: 04.09. - 29.09.2023
ETICS work, outside: 04.09. - 10.11.2023
Under-plastering, inside: 27.11. - 22.12.2023
Coating steel frames, railings: 03.04. - 22.04.2024
Graffiti protection, inside (corridor walls 2nd side + staircases): 15.04. - 10.05.2024
Surface plastering and painting work, inside: 15.04. - 10.05.2024
Main positions
ETICS work, partly with mineral. Plaster 1,075sqm, partly with clinker straps 1,110sqm, graffiti protection, 430sqm, MW insulation 2,185sqm, EPS base insulation 220 running metres.
Plastering work inside, under- and top-plaster 1.030qm, painting plaster/GK/concrete walls 2.320sqm, painting GK ceilings 2.200sqm, coating steel frames 12 pcs, coating steel railings and handrails 90lfm, 2K floor coating 45sqm