Construction of drinking water and sewage pressure pipelines
Construction of drainage systems
TWL
New laying of approx. 8237 m DN 80 to 1200 GGG/h
Re-laying of approx. 107 m DN 150 GGG in trenchless construction
Insertion of approx. 52 m DN 1000 in preh. Protection pipe DN 1200 GG/ 1224 StZMA
New installation of approx. 77 m DN 1000 St interim pipeline
Replacement of approx. 1072 m DN 80 to 1224 GG/GGG/St/Az/PVC against DN 80 to 1200 GGG/St
Replacement of approx. 1154 m DN 150 to 200 GG/Az with DN 150 to 200 GGG in trenchless construction
Replacement of approx. 51 m DN 100 to 200 GG/Az against DN 100 to 200 GGG (underpass)
Replacement of approx. 7 m DN 150 to 200 GGG/Az with DN 150 to 200 GGG (ground penetration)
Expansion of approx. 477 m DN 80 to 1200 GG/GGG/St
Extension of approx. 77 m DN 1000 St interim pipeline
Killing of approx. 7390 m DN 80 to 1400 GG/GGG/St/Az
ADL
New construction of approx. 64 m DN 200 to 1000 GGG/St in cut-and-cover construction
Pulling in approx. 9 m DN 800 St in preh. Protective pipe DN 1000 St
EP- Langrohrrelining mit Ringraumverfüllung ca. 326 m d 1100x65 PE / DN 1200 GG
PE- Close- Fit- Reduktionsverfahren ca. 1415 m d 1020x60 PE / DN 1000 GG/St
Replacement of approx. 509 m DN 200 to 1224 GG/GGG/St against DN 200 to 1000/ 1100x65 GGG/St/PE open design
Expansion of approx. 23 m DN 200 to 1000 GG/GGG
Killing of approx. 411 m DN 200 to 1000 GG/GGG/St
duct
Demolition/new construction of 2 manholes
Repair/conversion of 5 manholes
Demolition of 1 manhole
Demolition/new construction of 28 street drains
Demolition/ new construction of approx. 140 m DN 150 - 400 B/ Stz in cut-and-cover construction
New construction/demolition of approx. 26 m DN 400/ 800 interim pipeline
New construction of approx. 69.5 m DN 150 - 1200 GGG/ Stz/ CML-S-PE-FZM in cut-and-cover construction
Demolition of approx. 63 m DN 150 - 200 PVC-U/ KA 1200/950 B in cut-and-cover construction
Selective demolition/new construction approx. 2.5 DN 250 Stz in cut-and-cover construction
Spot repair DN 250-600 B/ GGG/ Stz
Road construction
approx. 16386 m² of road construction work in asphalt, concrete and stone roads and sidewalks
approx. 576 m² paved construction in sidewalks and cycle paths