Hospital Barmherzige Brüder München - Masterplan 1.BA // 3200-3 Master Builders - Steelwork Rampe
1. Quantities of main works:
- Interimsbau scaffold: manufacturing / holding / dismantling of a ramp construction from scaffolding components, fully enclosed,
- as weather protection L / W / H in m: approx. 35 / 1.50 / 2.40 m,
- Demolition: asphalt base and base courses 6 000 kg,
- Earthwork: excavation pit 40 m
- Reinforced concrete and concrete construction work: 7 m
- Steel construction: deconstruction existing steel construction lamp for statically improved reconstruction: approx. 26 000 kg of steel from various profiles, reassembly and static retrofitting by means of new columns / supports / extensions made of section steel: approx. 4 405 kg.
2. Execution times:
- Start: KW 30 (25.7.2019),
- End: KW 50 (9.12.2019).
Hospital Barmherzige Brüder München - Masterplan 1.BA // 3200-3 Master Builders - Steelwork Rampe
1. Quantities of main works:
- Interimsbau scaffold: manufacturing / holding / dismantling of a ramp construction from scaffolding components, fully enclosed,
- as weather protection L / W / H in m: approx. 35 / 1.50 / 2.40 m,
- Demolition: asphalt base and base courses 6 000 kg,
- Earthwork: excavation pit 40 m
- Reinforced concrete and concrete construction work: 7 m
- Steel construction: deconstruction existing steel construction lamp for statically improved reconstruction: approx. 26 000 kg of steel from various profiles, reassembly and static retrofitting by means of new columns / supports / extensions made of section steel: approx. 4 405 kg.
2. Execution times:
- Start: KW 30 (25.7.2019),
- End: KW 50 (9.12.2019).