Sundsvall Elnät AB is in need of partially renewing and rebuilding three existing 130/10 kV stations: M3, M4 and M6.
Power transformers for these receiving stations are already procured and will be replaced during the contract period by another contractor.
The procurement therefore includes the reconstruction of three existing reception stations M3, M4 and M6. The reconstruction of the stations consists of, among other things, a new additional 10kV compartment with associated new control facility, telecommunications facility, local power and auxiliary power systems and oil pits for transformers.
The procurement takes place in two stages, of which step 1 (this request) includes a qualification phase by interested bidders. Then, in step 2, the qualified tenderers will receive the specifications for further tendering and later be called for a tender review.
The FIFG is scheduled for the end of mid-April.
Construction ABT06
Rebuilding of three existing reception stations M3, M4 and M6. The reconstruction of the stations consists of, among other things, a new additional 10kV compartment with associated new control facility, telecommunications facility, local power and auxiliary power systems and oil pits for transformers.