Traffic route construction work, drainage canal works and construction of a bat protection wall for the municipal road west bypass Wenzenbach
The municipality of Wenzenbach is building a new municipal road "Westumfahrung". The subject of the invitation to tender is the civil engineering works for the construction of the municipal road. These are mainly traffic route construction works on a length of approx. 645 m, drainage pipes DN 150 to DN 400 on a length of 850 m and a bat protection wall on a length of 150 m.
Main road construction services:
1500 m3 Oberbodenarbeiten
12000 m3 of soil loosening
Supply 1100 m3 of floor
6340 m2 asphalt base and surface courses
1550 m2 Asphalttragdeckschicht
1200 m3 banquet production
5000 m3 Frostschutzschichten
560 m Borde made of natural stone
730 m of strips and gutters made of natural stone paving
360 m2 Pflasterdecken / Plattenbeläge
1780 m Road markings
550 m steel guard
2 St Buswartehallen
150 m Fledermausschutzwand H=4.0 m
Essential services Rainwater sewers
18 St Einsteigschächte
590 m Stahlbetonrohrleitung DN 300 – DN 400
260 m Kunststoffrohrleitung DN 150 - 400
1585 m3 Rohrleitungsgraben
Essential services Buildings :
1 St rainwater retention basin (earthworks) V=176 m3
25 m Stahlrohrdurchlass DN 2200
6 m Stahlbetondurchlass 1200/750
135 m3 infiltration system made of PP
18 m RW settling system DN 1000 (made of plastic pipes)
1 St RW settling tank made of reinforced concrete approx. V=66 m3
Essential services Utilities
30 m water pipe lowering AZ DN 200 / PE-HD DN 200
280 m Straßenbeleuchtungskabel