the purpose of the work is to renovate the runway and taxiways at Strasbourg-Entzheim airport. They concern more precisely the 05/23 runway and its two stop extensions, the Echo, Fox, Golf, Hotel, taxiways (up to about 155ml from the axial track) and VICTOR
The forecast estimate of the quantities to be used at this stage of the study is as follows:
- bituminous mix: 38,000 T
- planing: 15,300 m3
- coated gaskets/gutter: 6,600 ml
- belt leveling: 54,000 square meters (+36,000 square meters in TB)
- draining trenches: 50 ml
- F900 gutter: 145 ml made and 235 ml demolished
- recovery of gutter and gutter joints: 20 ml and 860 ml of joints
- lethalization: 205 h
- recessed lights trench: 220 ml
- 630 recessed beacon lights to be removed/rested (including 385 u to be supplied)
- 140 above ground fires to drop off/furnish /rest (and create massifs)
- 28 panels to remove/supply/rest (massifs to recreate and/or modify)
- 28 regulators to remove and replace
- 4 stop bars: 2 controllable and 2 permanent to remove/rest