Today, Nuremberg's Plärrer is of central importance both as a transport hub for private transport and public transport, as well as an urban space between the Gostenhof district and the old town. As a consequence of the exclusively traffic-related view of the 1970s, it is now an unsatisfactory place, both in terms of design and function, dominated by traffic. The overarching goal of holistic planning is the "reclamation" of the Plärrer as a public space.
Part of the planning is a reorganization of the urban development and traffic situation by redistributing the road traffic area and rerouting the tram and bus route with the creation of an attractive interchange stop between tram, bus and subway. This order includes the planning services in accordance with the HOAI Technical Equipment Service Profile.
The contract includes the planning for 4 to 6 properties in accordance with HOAI 2021 for the planning of the technical equipment of plant groups 1 to 4 in accordance with § 55 Scope: selected basic services as well as additional special services.
Cost estimate of construction work in euros net:
Object 1:
AT 1:4.100,00 Euros
AT 2:6.300,00 Euros
AT 3:1.800,00 Euro
AT 4:9.200,00 Euro
Object 2:
AT 1:15.400,00 Euros
AT 2:23.100,00 Euros
AT 3:9.800,00 Euros
AT 4:13.300,00 Euro
Object 3:
AT 1:16.400,00 Euros
AT 2:23.800,00 Euros
AT 3:2.900,00 Euro
AT 4:12.100,00 Euro
Object 4:
AT 1:28.800,00 Euro
AT 4:43.200,00 Euro
Object 5:
AT 1:7.200,00 Euro
AT 4:10.800,00 Euros
Object 6:
AT 1:35.100,00 Euros
AT 2:18.500,00 Euros
AT 3:3.700,00 Euro
AT 4:35.100,00 Euros
Planned dates:
Milestones:
Planungsbeginn 11.01.2024
Approval planning handover of documents to AG 06.08.2024
Completion of construction 06.07.2028