19O30233 Chemnitz Chemnitz Chemnitz, new accommodation Döbeln Police Station
Structural work.
- about 2 500 m 3 Construction pit excavation, investigation and disposal as well as soil application and modeling,
- approx. 195 m underground lines with 4 inspection shafts,
- approx. 515 m of drainage pipes including inspection shafts,
- About 1 065 m 2 Sealing work vertically and horizontally,
- about 3 300 m 2 Masonry in different qualities including detailed training,
- about 275 m 3 Reinforced concrete for foundations,
- about 1,200 m 2 Floor tiles,
- about 2 000 m 2 Reinforced concrete / in-situ concrete, partly with exposed concrete requirements,
- about 2 800 m 2 Reinforced concrete ceilings, as filigree corners,
- 8 flights of stairs,
- 4 prefabricated platforms,
- Corresponding in-concrete installation, empty pipes, media inlets, etc.