The construction project includes the extensive renovation of the technical facilities and
Equipment of the building 201. Due to the technical condition and changed tenant-specific requirements, a mere replacement of the technology is not expedient. Therefore, existing ventilation and smoke extraction ducts as well as technical systems,
which supply, dismantle and rebuild the project B-001568. The contract is divided into two construction phases. The first phase of construction has been largely completed. This order includes the ventilation and air-conditioning technology for the second construction phase (WEST).
Further information under II.2.4
Start of execution: approx. 2nd quarter 2024
End of execution: approx. 3rd quarter 2025
Approximate scope of the measure:
Fire dampers:
• With drive (rectangular): approx. 148 pieces
• Without drive (rectangular): approx. 302 pieces
• DN up to 315 (without motor): approx. 251 pieces
• DN up to 315 (with motor): approx. 135 pieces
Volumenstrombegrenzer:
• Round: approx. 944 pieces
• With motor: approx. 51 pieces
Pressure regulator:
• With motor: approx. 49 pieces
Kanalleitung:
• Galvanized: approx. 4,190 m²
Fittings:
• Galvanized: approx. 2,860 m²
Nozzle/grid cut-out:
• Up to 0.60 m²: approx. 1,150 pieces
Wickelfalzrohr:
• (DN 100 - DN 315): ca. 4.012 m
Fittings (elbows, branches, reducers):
• Approx. 4,300 pieces
Ceiling air diffuser and ceiling swirl outlet:
• Approx. 1,136 pieces
Ventilation systems (TKA):
• Approx. 7 pieces
Rauchdruckanlagen:
• For 2 stairwells
MRA-Anlagen
• Approx. 2 pcs up to max. 3000 m²/h
Entrauchungsklappe
• Ca. 17 St,
Entrauchungsleitung
• Ca. 1.105 m²
For the receipt of the complete procurement documents, the information under VI.3 must be taken into account. Interested companies must submit a confidentiality agreement.
The confidentiality declaration is part of the document "Self-declaration of suitability" or "Proof of suitability for the application to participate".