The Asklepios Klinikum Uckermark-Schwedt intends in the course of the current refurbishment and further development of the hospital the conversion and the extension of the component AK8 on the 2nd floor to a new central emergency room.
The entrance to the emergency room will be an extension to house elevators and stairwell. In addition, the extension on the second floor is connected via a catwalk to the new helipad.
The conversion is mainly planned in the 2nd floor of the AK8. The floors below remain in use during the construction phase
Heating equipment:
- dismantling pipelines about 126 m,
- dismantling radiators approx. 6 St,
- Radiator div Ausf. about 7 hours,
- threaded tube about 80 m,
- Heating circulation pump approx. 2 hours
Door air curtain 1 pc.
plumbing
- Drain pipes div Exec. about 160 m,
- stainless steel pipes approx. 170 running meters,
- WC facilities about 3 hours,
- hand basin about 9 St,
- Dismantling WC / shower / WT systems.
ventilation
- Air duct div. Execute. about 11 m
- spiral folded pipe approx. 100 m,
- Dismantling ventilation.
MSR installation
- connecting BS-flaps,
- Telecommunications lines approx. 600 m.