Belagsaufbruch 3'075 t
Gleisabbruch WSB-Trassee 125 m3
Demolition of edge closures 2,000 m
Fundationsschichtabtrag 4'000 m3
Installing a foundation layer 4,500 m3
Randabschlüsse 2'000 m
Base and binder courses bituminous 2,700 t
Bituminous surface courses 1,020 t
Mastic asphalt MA16 and MA11 H 260 t
Build a plan 8'500 m2
Verkehrswegebeton (2 Busbuchten) 340 m2
Retaining and plinth walls in in-situ concrete 300 m
Strassenentwässerung PE Ø 160 mm 230 m
Schlammsammler / Einlaufschächte 40 St
Sewerage collection line up to DN600 265 m
Control schacht Ø 600/1'100 mm 6 St
Sewer rehabilitation with inliner DN300 55 m
Cable pipe block (DN55 to DN150) 3,200 m
Trench excavation, sewerage, water, gas 2,600 m3
Belagsaufbruch 3'075 t
Gleisabbruch WSB-Trassee 125 m3
Demolition of edge closures 2,000 m
Fundationsschichtabtrag 4'000 m3
Installing a foundation layer 4,500 m3
Randabschlüsse 2'000 m
Base and binder courses bituminous 2,700 t
Bituminous surface courses 1,020 t
Mastic asphalt MA16 and MA11 H 260 t
Build a plan 8'500 m2
Verkehrswegebeton (2 Busbuchten) 340 m2
Retaining and plinth walls in in-situ concrete 300 m
Strassenentwässerung PE Ø 160 mm 230 m
Schlammsammler / Einlaufschächte 40 St
Sewerage collection line up to DN600 265 m
Control schacht Ø 600/1'100 mm 6 St
Sewer rehabilitation with inliner DN300 55 m
Cable pipe block (DN55 to DN150) 3,200 m
Trench excavation, sewerage, water, gas 2,600 m3