Refurbishment of Niederberg Comprehensive School: Interim container
Delivery, assembly, provision and dismantling of the interim container system; the service life is a total of 20 months (1st BA and 7 months 2nd BA.).
The city of Neukirchen-Vluyn is planning to extensively rebuild, renovate and modernize the municipal comprehensive school Niederberg at Tersteegenstraße 85 and 87 in Neukirchen-Vluyn according to current pedagogical ideas.
The service of the contractor (contractor) is the delivery and installation of the modular system with the described equipment (two-storey, 16 classrooms) including the necessary work and assembly planning. The Contractor is responsible for the compatibility of the components with each other. The work and assembly planning, based on the bidder's system, must be completed no later than 14
days after placing the order. All rooms are to be built in modular construction and implemented according to the planning. After termination of the lease with the city of Neukirchen-Vluyn, the container facility must be taken over by the
Installers can be dismantled.
The client's services essentially include:
- Obtaining all necessary permits
- Coordination with the approval and acceptance authorities as well as the local suppliers
- Guarantees of access to the installation site and free working areas for heavy-duty vehicles and mobile cranes up to 30 tons according to this site plan, only after prior consultation and on-site visit with the contractor and client
- Production of the load-bearing soil/subsoil for the installation of the container system by the client in accordance with the soil survey.
- Indication of the loads by the AN container.