Maintenance of the Sandbank Windfarm Steel structures and cable (IAC) with the exception of WTG tower maintenance and the exception of improvements and Repair (Troubleshooting)(overhaul). Respectively optional Maintenance of the Dantysk Windfarm Steel structures with the exception of WTG tower maintenance and the exception of improvements and Repair overhaul).
The contract shall comprise the scheduled and unscheduled maintenance covering inspection, servicing and repairs (Troubleshooting only) for the steel structures and additional electrical and mechanical systems of the Sandbank Offshore Windfarm. The scope of work shall cover the work planning, execution and back-reporting of the conducted maintenance of seventy-two (72) wind turbine generators (WTG) foundations and one jacket structure of the Offshore Substation (OSS).
1. Monopile (MP).
A-I11 Inspection Flange TP/MP Connection Bolts, Servicing Retorque Bolts.
2. Transition Piece (TP) mainly based on WKP-Concept (ITP) and Manufacturers Maintenance Manual.
A-I21 Visual Inspection Condition and Coating TP Inner and Outer Hull, if necessary Repair (Troubleshooting).
A-I22 Visual Inspection Safety Anchor Points (Work Platform) and load test.
A-I23 Visual Inspection all external and internal ladders, sliding gates, etc. (welded/connection points).
A-I24 Visual Inspection boat landing structure (welded/connection points).
A-I25 Support to annual Inspection/Servicing/Repair (Troubleshooting only) of the OEM Davit Crane through Contractor.
A-I26 Visual Inspection/Servicing Fall-Arrest System (Latchways) including guide rail, if necessary Repair (Troubleshooting)(Troubleshooting).
A-I27 Visual Inspection ICCP-System, if necessary Repair (Troubleshooting).
A-I28 Visual Inspection UPS System (Benning), if necessary Repair (Troubleshooting).
A-I29 Visual Inspection Navigation Light System including Electrical Distribution System and Cabling (Sabik), if necessary Repair (Troubleshooting).
3. Jacket Offshore Substation (OSS) mainly based on WKP-Concept (ITP).
A-I31 Visual Inspection Jacket and Steel structures (Rope Access).
II. Maintenance below Water Level LAT.
1. Monopile (MP) (Campaign May-September 2018), mainly based on WKP-Concept (ITP) and Manufacturer Maintenance Manual.
A-II11 Visual Inspection Scour Protection System.
A-II12 Visual Inspection ICCP-System, if necessary Repair (Troubleshooting) (ROV).
A-II13 Visual Inspection Boat Landing and all Ladders (welded/connection points) if necessary Repair (Troubleshooting).
A-II14 Visual Inspection Marine Growth and cleaning, if necessary (ROV).
2. Jacket-Structure (OSS) mainly based on WKP-Concept (ITP) and Manufacturers Maintenance Manual.
A-II21 Inspection Scour Surveillance.
A-II22 Inspection Conditions and Coating, if necessary Repair (Troubleshooting) (ROV/Diving).
A-II23 Inspection Boat Landing and all Ladders (welded and connection points) if necessary Repair (Troubleshooting).
A-II24 Marine Growth Inspection, cleaning if necessary (ROV).
A-II25 Global Visual Inspection, Jacket and Steel Structures (ROV/Diving).
A-II26 Hotspot Inspection, Jacket and Steel Structures (ROV/Diving).
3. Cable Burial (IAC).
A-II31 Periodic Inspection IAC (Sonar/ROV).
The Employer decides whether this nonbinding option shall be exercised. The scope basically focusses on the scheduled and unscheduled maintenance above and below water level (LAT). All maintenance works shall be conducted in strict accordance with the applicable national and international legislation, standards and regulations, the requirements of the Bundesamt für Seeschifffahrt und Hydrographie (BSH) the requirements of the Employers designated certifier respectively the Employer Requirements.
I. Maintenance above Water Level LAT.
1. Monopile (MP).
B-I11 Visual Inspection Flange TP/MP Grout Connection.
2. Transition Piece (TP) mainly based on WKP-Concept (ITP) and Manufacturers Maintenance Manual.
B-I21 Visual Inspection Condition and Coating TP Inner and Outer Hull, if necessary Repair (Troubleshooting).
B-I22 Visual Inspection Safety Anchor Points (Work Platform) and load test.
B-I23 Visual Inspection all external and internal ladders, sliding gates, etc. (welded/connection points).
B-I24 Visual Inspection boat landing structure (welded/connection points) if necessary Repair (Troubleshooting).
B-I25 Visual Inspection/Servicing of the Davit Crane. If necessary conduct Repair (Troubleshooting).
B-I26 Visual Inspection/Servicing Fall-Arrest System (Latchways) including guide rail, if necessary Repair (Troubleshooting).
B-I27 Visual Inspection/Servicing (inside) Sacrificial Anodes.
B-I28 Visual Inspection UPS System (Benning), if necessary Repair (Troubleshooting) (Troubleshooting).
B-I29 Visual Inspection Navigation Light System including Electrical Distribution System and Cabling (Sabik), if necessary Repair (Troubleshooting).
3. Jacket Offshore Substation (OSS) mainly based on WKP-Concept (ITP).
B-I31 Visual Inspection Jacket and Steel structures (Rope Access).
4. Jacket Offshore Accommodation Platform (OAP) mainly based on WKP-Concept (ITP).
B-I41 Visual Inspection Jacket and Steel structures (Rope Access).
II. Maintenance below Water Level LAT.
1. Monopile (MP) mainly based on WKP-Concept (ITP) and Manufacturer Maintenance Manual.
B-II11 Visual Inspection Scour Protection System.
B-II12 Visual Inspection (Outside) ICCP-System, if necessary Repair (Troubleshooting)(Troubleshooting) (ROV).
B-II13 Visual Inspection Boat Landing and all Ladders (welded/connection points) if necessary Repair (Troubleshooting).
B-II14 Visual Inspection Marine Growth and cleaning, if necessary (ROV).
2 Jacket-Structure (OSS/OAP) mainly based on WKP-Concept (ITP) and Manufacturers Maintenance Manual.
B-II21 Inspection Scour Surveillance.
B-II22 Inspection Conditions and Coating, if necessary Repair (Troubleshooting) (ROV/Diving).
B-II23 Inspection Boat Landing and all Ladders (welded and connection points) if necessary Repair (Troubleshooting).
B-II24 Marine Growth Inspection, cleaning if necessary (ROV).
B-II25 Global Visual Inspection, Jacket and Steel Structures (ROV/Diving).
B-II26 Hotspot Inspection, Jacket and Steel Structures (ROV/Diving).
3. Cable Burial (IAC).
B-II31 Periodic Inspection IAC (Sonar/ROV).