Roofing work as part of the construction of a new multi-purpose building at the Degerfeldschule in 35510 Butzbach
General building description:
In the course of the expansion of all-day care, a 3-storey multi-purpose building is to be built as an extension in the northern area of the Degerfeldschule in Butzbach.
It is planned to erect the building with a partial basement. In the basement, the technical rooms and numerous storage rooms are arranged at the same time. On the ground floor, a canteen area with cooking kitchen, two offices and several sanitary facilities are planned. In addition to classrooms and group rooms, a spacious exercise room including changing rooms and two sanitary facilities will be created on the 1st floor. On the 2nd floor, classrooms, group rooms, differentiation rooms, offices and sanitary facilities will be created. The play and break corridors on the two upper floors can also be "switched" during breaks through doors to the games and break rooms of the floors.
The multi-purpose building is given two stairwells and an escape staircase.
Barrier-free access to the floors takes place in the stairwell to the south via an elevator system. An escape staircase will be arranged on the western part of the building. The 3-storey semi-basement building is a solid structure with a flat roof. In accordance with the Hessian Building Code (HBO), the new building is assigned to building class 5, special construction. Due to a limited number of 200 people in the dining room/canteen area, this is not a meeting place according to meeting place regulations.
In the north, the city of Butzbach is planning the construction of an access road, which replaces the current paved dirt road and will serve as an access road for the new construction area after completion. Due to this measure, the changes to the northern property boundary of the school also took place. It is currently planned to start construction of this new road in the summer of 2022. Thus, the completion of the road would be before the completion of the new building of the multi-purpose building (completion of new building planned in December 2023).
Supply, disposal and rescue vehicles (ambulance/fire brigade) can then also directly reach the new extension of the Degerfeld School on the back side.
Trade union description:
Roofing work / Green retention roof
- Bauwerksabdichtung KG and ground floor: 900 m²
- Densification of window elements on the ground floor: 75 m
- Dachabdichtungsarbeiten: 900 m²
- Attikenausbildung: 125 m
- Green retention roof with water retention boxes WRB 900 m²
- Absturzsicherungen (Seilsicherungssystem) 128 m
Due date:
Start of the structural implementation expected at the earliest in the 38th week 2022
End of the structural implementation expected in the 45th week 2022