Construction of a new workshop building for the departments of construction, painting and personal care north of the existing workshop building. The new building will be built as a reinforced concrete solid construction with ETICS façade and wood-aluminium element windows according to valid EnEV with flat roof construction.
Niederspannungshauptverteilung 1 St.
Blindstromkompensationsanlage 1 St.
Einzelstandschrank 3 St.
Kleinverteiler 3 St.
Feldverteiler 10 St.
Residual current circuit breaker 100 pcs.
Miniature circuit breaker 400 pcs.
Sheathed cables/cables 30,000 running meters
Installationsgeräte 1.500St.
LED luminaires recessed, surface-mounted, pendulum 500 pcs.
Sicherheitsbeleuchtungsanlage 1 St.
KNX-Anlage 1St.
PA system 1pc.
SHEV system 1 pc.