Drywall work and interior doors.
The following work is planned as part of the construction project:
1st construction phase new building:
- Drywall as facing shells approx. 160 m
- suspended ceilings total approx. 800 m
- Installation of 5 doors, wood door leaf, steel frames as DS and RS T30 RS doors. 1 pc steel sheet door T30 RS including frame;
- 2 toilet partitions consisting of 4 and 12 cabins.
2nd stage of construction:
- drywall approx. 70 m
- suspended ceilings total approx. 600 m
- Installation of 6 single-leaf doors. T30-RS, door leaf wood, steel frame, 2 pieces of 2-leaf doors T30 RS doors.